(1) After the installation of each equipment, carefully debug the conveyor to meet the requirements of the drawing.
(2) Each reducer, the moving parts are filled with corresponding lubricating oil.
(3) After the conveyor is installed to meet the requirements, each single equipment is manually worked and tested, and the conveyor is combined to debug the conveyor to meet the requirements of the action.
(4) Debug the electrical part of the conveyor. Including the debugging of conventional electrical wiring and action, so that the equipment has good performance and achieves the designed function and state.